logo

OUR PROJECTS

ROYAL GARDEN SHERATON FIRE TANK
PROJECT LOCATION

El-Haram

PROJECT YEARS OF AWARD

2002

PROJECT MAIN CONTRACTOR

Concrete Plus

CONCRETE PLUS ASSIGNMENT

Main contractor for concrete works (shuttering, bar-bending, concrete pouring, concrete leveling) using Concrete plus tools. plywood and equipment's 

CONTRACT TOTAL VALUES

20,000,000 EGP

PROJECT SCHEDULE

10 months

PROJECT GENERAL CONSULTANT

Dr. Aly Abd el-Rahman

PROJECT DETAILS

 150m3 with 2 vents. fair face fire tank with steel cover and epoxy painted