PROJECT LOCATION

35km North Marsa Alam city- Abo Dabab Bay

PROJECT YEARS OF AWARD

2005

PROJECT MAIN CONTRACTOR

Concrete Plus

CONCRETE PLUS ASSIGNMENT

Main contractor for concrete works, masonry, waterproofing and plastering from scratch (shuttering, barbending, concrete pouring, concrete leveling) using Concrete plus scaffolding system and equipment's for whole buildingsĀ 

CONTRACT TOTAL VALUES

50,000,000 EGP

PROJECT SCHEDULE

16 months

PROJECT GENERAL CONSULTANT

EHAF

PROJECT DETAILS

Total constructed area 24000 m2. Main Building total areal 2000m2. restaurant. special restaurant, kitchen, shops, Gym, admin., offices, ramps, piano lounge, reception and lobby covered with concrete dome on height of 32m diameter 20m. Distillation Plant (Production Building -l 000m3 rested water tank - clarifying basin). Power Plant (generator house 1000m2). Irrigation Tank. Sewage Plant