logo

Organization charts

FELO RESORT-MARSA ALAM
PROJECT LOCATION

6th October City

PROJECT YEARS OF AWARD

2010

PROJECT MAIN CONTRACTOR

Concrete Plus

CONCRETE PLUS ASSIGNMENT

Main contractor for concrete works. masonry, waterproofing and plastering from scratch (shuttering, barbending, concrete pouring, concrete leveling) using Concrete plus scaffolding system and equipment's for whole buildingsĀ 

CONTRACT TOTAL VALUES

60,000,000 EGP

PROJECT SCHEDULE

16 months

PROJECT GENERAL CONSULTANT

Decor (Eng. Omar EI-Gouneemy)

PROJECT DETAILS

Total constructed area 60000 m2. 425 Touristic Rooms around 32000 m2 total constructed area. Main Building on 6500 m2 2 floors with its ramps, double height entrance, Conference rooms. ball rooms around 9000 m2and 5 buildings 450 m2 each for staff housing. Distillation Plant. Irrigation Tank. Sewage Plant. Hard EscapeĀ